Half the diameter.
Twice the capacity.

How siphonic drainage works, the hydraulic logic behind it, and the materials and standards it is built to. The whole system, from the diagram to its counterpart on site.

Multiple Geberit Pluvia roof outlets connect through a zero-slope collector pipe to a single vertical stack — the basic unit of the siphonic system. On large roofs several groups are installed; each group has its own stack.

01Component

Roof outlet — Geberit Pluvia outlet

The Pluvia roof outlet draws water from the roof surface without admitting air; the function disc and anti-vortex baffle work together. Unless air ingress is prevented, the system cannot hold a vacuum and priming will not begin.

14 — 100 L/s · by model
02Component

Collector pipe — zero slope

A horizontal HDPE line that carries the flow of multiple roof outlets and runs beneath the beams. Because the slope is zero, it does not interfere with the building's architecture; every joint is made by butt welding to DVS 2207.

0° slope · ø 50 — ø 315 mm
03Component

Vertical stack — the vacuum driver

A vertical HDPE line positioned at every other column. The falling water column places the collector pipe under vacuum (typically −0.45 bar, peak ≤ −0.78 bar). The system primes and transitions to full-bore flow.

4 — 6 m/s · ψ = 1.0 full-bore flow
Typical Logistics Roof · Schematic
ROOF SURFACE — INDUSTRIAL ROOF DECKGEBERIT PLUVIAOUTLET 01GEBERIT PLUVIAOUTLET 02GEBERIT PLUVIAOUTLET 030° — ZERO SLOPE · HORIZONTAL COLLECTORGEBERIT HDPE · BUTT WELDING (DVS 2207)CONCRETE COLUMN⌀ 110 mmHDPE DOWNPIPEDISCHARGE → GROUNDGROUND LEVEL−0.45 BARVACUUM · PEAK ≤ −0.784 — 6 m/sFULL-BORE FLOWTS EN 12056-3GEBERIT PROPLANNER
Bilgin uygulaması — beton fabrika iskeletinde kolon yanlarına inen siyah HDPE iniş boruları, kiriş altı yatay kolektörler
The schematic on site
A stack at every other column, a collector pipe beneath the beams.

The diagram above is the technical counterpart of exactly this scene — a zero-slope horizontal HDPE collector pipe feeds the vertical stacks that connect to selected columns via elbows.

Hydraulic Logic

Not gravity —
pressure does the work.

Thanks to the air barrier (anti-vortex) placed at the roof outlet, siphonic drainage fills the pipe completely with water from the point of entry. The negative pressure generated inside the pipe draws water from the collector pipe toward the stack, evacuating it horizontally.

  1. Phase
    01

    The air is swept out

    As rainfall intensifies, the anti-vortex baffle of the Geberit Pluvia roof outlet keeps air from entering; the air within the line is swept from the collector pipe toward the stack.

  2. Phase
    02

    Full-bore flow

    The pipe cross-section fills 100% with water. No air pocket remains. This is the single condition that makes the siphon possible — TS EN 12056-3 §4.1.

  3. Phase
    03

    Negative pressure builds

    The water column falling through the stack creates negative pressure in the system. Pressure in the horizontal line drops below atmospheric; the system begins to draw water off the roof.

  4. Phase
    04

    The line reaches equilibrium

    A Bernoulli energy balance is established: the height difference fully offsets the friction losses (HL) along the line. Flow stays stable at 4–6 m/s, carrying several times the flow rate of a gravity system.

Technical Specifications

A line
signed off to standard.

Every system is delivered to international standards, with a BIM calculation and certified welding procedures. The specifications below are the technical index of a typical industrial installation package from Ahmet Bilgin Yapı Malzemeleri.

StandardTS EN 12056-3
Pipe MaterialGeberit HDPE (high-density polyethylene)
Pipe Diametersø 40 — ø 315 mm (DN 50/56/75/90/110/125/160/200/250/315)
JointingButt welding, electrofusion (DVS 2207-1 / DVS 2207-15 certified)
Roof OutletGeberit Pluvia · function disc / anti-vortex · 14 / 25 / 45 / 60 / 100 L/s models
Hydraulic CalculationGeberit ProPlanner — Revit BIM plug-in (Bernoulli + Darcy-Weisbach)
Operating VacuumTypical −0.30 / −0.45 bar · peak ≤ −0.78 bar (TS EN 12056-3 limit)
Flow Velocity4 — 6 m/s full-bore flow
Degree of Fillingψ = 1.0 (after priming)
Support SystemGalvanized steel clamps, 0.8 m for ø50-90 · 1.1 m for ø110 · 1.2 m for ø125
Operating Temperature−40 °C → +60 °C
Service Life≥ 50 years (Geberit HDPE)
Fire ClassB-s1, d0 (with flame-retardant variant)
Warranty2-year Bilgin workmanship + Geberit HDPE manufacturer system warranty
HDPE stack mounted against a concrete column — on site.
ON SITE · ⌀ 110 mmedge of concrete column
One installation, five frames

From bare plot to first
downpour.

The timeline of a single Bilgin project: from bare ground to building enclosure, through to how the system engages in the first rainfall. At every stage, engineer supervision and step-by-step documentation are applied.

A plot, an intent
01
Before
A plot, an intent

Bare ground, blue sky. Not a single line yet — but the roof plan, rainfall data, and collector pipe route are already taking shape on the ProPlanner screen.

The columns go up
02
Frame
The columns go up

Concrete columns and beams take their places. Bilgin is engaged at this stage: the stacks are positioned according to the column layout, and the bracket plan for the under-beam runs is finalized.

The first HDPE stack beside a column
03
Siphonic goes in
The first HDPE stack beside a column

The frame is complete and certified welders begin placing the siphonic lines. A vertical HDPE stack at every other column — the horizontal collector pipe above directs the water it gathers from multiple Pluvia roof outlets to this point.

Façade, light, silence
04
The building is enclosed
Façade, light, silence

The blue sandwich-panel façade is closed up. A system that is unseen but ready: Pluvia roof outlets on the roof, vertical stacks beside the columns, collection at ground level. The building enters its first evening.

The system primes
05
First downpour
The system primes

Rainfall intensity crosses the threshold. The anti-vortex baffle disc prevents an air pocket; the water column falling through the stack creates negative pressure in the system. Within seconds full-bore flow begins — water never pools on the roof.