Every step
is calculated.

From calculation to testing, the order in which a siphonic line is built. Each of the five steps is tied to a document; none is left to guesswork.

In a siphonic system, every meter of pipe must be the diameter defined by the calculation, and every joint must be made with certified welding. This discipline is the only condition that enables priming and holds the vacuum. At Ahmet Bilgin Yapı Malzemeleri the procedure is defined end to end — every step on site has its counterpart at the desk.

  1. 01
    Hydraulic calculation

    The engineer at the desk first

    The roof plan and local rainfall data are entered into Geberit ProPlanner; the pressure loss of each pipe segment is derived using the Bernoulli and Darcy–Weisbach equations. Output: a certified hydraulic calculation report.

    Geberit ProPlanner · BIM (Revit)
  2. 02
    Site survey

    We go up on the roof and measure

    Our engineer measures the roof in person on site. Column layout, bracket plan and collector pipe route are finalized according to the roof structure — the desk plan is reconciled with on-site reality.

    Isometric · bracket/clamp plan
    Bilgin site team — certified workers installing brackets on site
    Site · under engineer supervision
  3. 03
    Calculation-based supply

    Project-specific materials

    Pipe diameters and fittings are supplied in exact accordance with the list defined by the hydraulic calculation. Nothing is pulled off the shelf; every line is prepared to order.

    Geberit HDPE · ø 40 — ø 315 mm
    Original Geberit HDPE fitting, yellow authenticity label visible
    Original Geberit fitting — labeled
  4. 04
    Certified welding

    Every joint logged to DVS 2207

    Butt welding and electrofusion are performed by our DVS 2207-certified welders. Every joint is logged for temperature, pressure and time; the engineer supervises on site.

    DVS 2207-1 (butt) · 2207-15 (electrofusion)
    Butt-welding machine — two HDPE pipe ends in clamps, heating plate in the center
    Butt welding · clamp + heating plate
  5. 05
    Testing & commissioning

    Proof before going live

    The line is delivered with a pressure test, visual inspection and a commissioning run. The test report, welding log, hydraulic calculation and warranty certificate are handed over together.

    Pressure test · warranty file
    Completed HDPE collector line, fixed to the ceiling with galvanized clamps
    Handover · completed collector pipe
Delivery package

Hydraulic calculation report · Isometric (DWG + PDF) · Welding log · Test report · Bilgin workmanship warranty certificate.